Working with automatic mode

Create project with Automatic model chain.

Right click on Automatic mode task in Project Explorer and select “Run new automate”.

Input neccesary data in RodosLite windows.

Set date of release. Release date should be corresponded to available measurement data. This means that release date in RodosLight should be set to date in available measurement data.

Make sure that On site meterological data on RodosLight Weather tab is selected.

Automatic tasks works completly on data from JRodos database RTDB. Rttf-files should be imported to RTDB before use. This can be done either manually by selection menu: Measurments→Import measurments (default data is in RodosHome/ronet/rorttf/mast) or automatically in background by JRodos system. For this purpose RTTF files should be put to <JRodos>/Automatic/RTTF

In Automatic mode the system calculates with first time interval for RodosLite and continue with next intervals as long as appropriate measurments are available, then waits for new ones. If measurment data for the first time interval is not existing, system shows warning and tries to find more earlier data in RTDB up to administrator-defined criteria time steps.

If system is waiting for next timestep data but only later data is incoming (e.g. system has calculated with 11:00, now waits for 11:10, but this is not coming but sometimes later the 11:20), the system then checks how many files are missing in between, if number is below administrator-defined criteria system uses last file for intermediate interval as replacement for missing file and then continues with latest file; otherwise system stops with error message.

In Automatic mode prognosis calculation is started after administrator-defined number of Diagnosis calculation steps. Prognosis calculation contains (ALSMC and EMERSIM models).

To stop task a user should make a right click on running Automatic mode task and select Stop. After it a user should wait until the last calculation task will be finished. Please note! Waiting untill calculation is finished is neccesary for correct resuming!

After calculation is stooped project can be saved to database or resumed. Stopped and saved project can be loaded from database and resumed calculation.

To resume calculation right click on Automatic mode task in Project Explorer and select “Resume stopped automate”.