Line 5: Line 5:
 {{jrodos:​automatic.mode:​dialog.gif|}} {{jrodos:​automatic.mode:​dialog.gif|}}
  
-Select ​"Run new automate"​.+Right click on Automatic mode task in Project Explorer and select ​"Run new automate"​.
  
 {{jrodos:​automatic.mode:​start.new.run.gif|}} {{jrodos:​automatic.mode:​start.new.run.gif|}}
Line 13: Line 13:
 Set date of release. Release date should be corresponded to available measurement data. This means that release date in RodosLight should be set to date in available measurement data. Set date of release. Release date should be corresponded to available measurement data. This means that release date in RodosLight should be set to date in available measurement data.
  
-Select ​''​On site meterological data''​ on Weather tab odf RodosLite.+Make sure that ''​On site meterological data''​ on RodosLight ​Weather tab is selected.
  
 {{jrodos:​automatic.mode:​on.site.data.gif|}} {{jrodos:​automatic.mode:​on.site.data.gif|}}
Line 26: Line 26:
 In Automatic mode prognosis calculation is started after [[models:​automatic:​files|administrator-defined number]] of Diagnosis calculation steps. Prognosis calculation contains (ALSMC and EMERSIM models). In Automatic mode prognosis calculation is started after [[models:​automatic:​files|administrator-defined number]] of Diagnosis calculation steps. Prognosis calculation contains (ALSMC and EMERSIM models).
  
-To stop task a user should make a right click on running Automatic mode task and select Stop. After it a user should wait until the last calculation task will be finished. Then project can be saved to database or resumed. Also stopped and saved project can be loaded from database and resumed calculation.Please note! Waiting untill calculation is finished is **neccesary** for correct resuming!+To stop task a user should make a right click on running Automatic mode task and select Stop. After it a user should wait until the last calculation task will be finished. Please note! Waiting untill calculation is finished is **neccesary** for correct resuming!
  
 {{jrodos:​automatic.mode:​stop.gif|}} {{jrodos:​automatic.mode:​stop.gif|}}
 +
 +After calculation is stooped project can be saved to database or resumed. Stopped and saved project can be loaded from database and resumed calculation.
 +
 +To resume calculation right click on Automatic mode task in Project Explorer and select "​Resume stopped automate"​.
 +
 +{{jrodos:​automatic.mode:​resume.gif|}}